Capital Project No. 3177 W. Prien Lake Road Widening from Cove Lane to Ihles Road
Capital Project No. 3177 – W. Prien Lake Road Widening from Cove Lane to Ihles Road
Updated: January 29, 2024
When did construction actually start?
The road construction began in August of 2021
Full project scope overview: Click Here to See Exhibit Maps
Roadway Pavement
West Prien Lake Road
- West Prien Lake Road will be reconstructed from Cove Lane south to Ihles Road. This includes a new 4-lane concrete roadway that will be widened to include left turn lanes at the Sale Road intersection. This intersection will be a signalized intersection.
Sale Road
- Sale Road has been reconstructed to continue the 3-lane concrete roadway from Rue Chan Ann Lane west to W. Prien Lake Rd.
Henderson Bayou Road
- Henderson Bayou Road, from Indian Bay Drive east to West Prien Lake Road, will be reconstructed and widened in order to provide dedicated left and right turn lanes for eastbound traffic entering Prien Lake Rd.
Sidewalks
- 8-foot-wide bike path on west side of West Prien Lake Road
- Traditional sidewalk on east side of West Prien Lake Road and north side of Sale Road
Water & Sewer Improvements
- This project also includes upgrades and expansions to the water and sewer systems. These system upgrades are intended to better provide for existing residents as well as prepare for continued growth in this area.
Drainage Improvements
- This project includes constructing a new underground drainage system with two new major outfalls into Henderson Bayou. One on the north side of West Prien Lake Rd, west of Ihles Rd, and the other on the north side of Henderson Bayou Road near the bridge. This new system will be an upgrade of the existing to serve the local area more adequately.
Where are we now?
- The vast majority of the drainage infrastructure included in the project has been installed. Some smaller drainage projects on the north end of the project and also the east side near Sale/Henderson Bayou Rd remains.
- The reconstruction of the intersection of West Prien Lake Road and West Sale Road is complete.
- The reconstruction Sale Road is complete.
- The paving of West Prien Lake Road, south of Sale Road, is nearing completion. Weather permitting; contractors anticipate opening West Prien Lake Road, south of Sale Road, to 2-way traffic towards the 1st week of March.
What's next and what changes can be expected?
- Once West Prien Lake Road, south of Sale Road, has been opened to 2-way traffic, the portion of West Prien Lake Road, between the roundabout & Sale Road will become open to southbound traffic only. It will remain this way for approximately one (1) year.
- Paving will proceed north by completing the west half and transferring traffic to new pavement. Then east half will be paved. The paving operations will proceed north. Click Here to See Exhibit Maps
When will both lanes be open?
- We anticipate 2-way traffic being opened in Spring 2025
When will project be completely finished?
- Summer 2025
To receive the latest notices on closures and detours, please submit your email address to engineering@cityoflc.us.
Project Updates:
Update: Thursday, March 28, 2024 - West Prein Lake Road / Henderson Bayou Road Closure Extension
Update: Tuesday, November 19, 2024 - West Prien Lake Road Traffic Flow Change Ahead